In the Twin Cities metro area, kitchen remodel costs typically range from $25,000 to $175,000 or more, depending on cabinetry, layout changes, and finish level. Below is a breakdown of what drives that range so you can see roughly where your project fits before you request a quote.
Cost by scope
Defined-Scope Refresh
$25,000--$45,000
Cabinet refacing or repaint, new hardware, new countertops and backsplash on the same footprint, and an appliance swap. No layout or plumbing changes.
Full Remodel
$55,000--$95,000
New semi-custom cabinetry, layout adjustments within the existing footprint, new countertops, flooring, lighting, and appliances, plus minor plumbing or electrical relocation.
Premium Custom
$100,000--$175,000+
Full layout change, wall removal, custom cabinetry, premium countertop material, professional-grade appliances, and structural work or footprint expansion.
Most of the kitchen projects we complete land in the Full Remodel to Premium Custom range. Kitchens tend to be a homeowner's flagship remodel, not a quick refresh.
What moves the budget most
Layout changes are the single biggest swing. Moving a sink, range, or island relocates plumbing and gas lines. After that, cabinetry tier is the largest single line item, followed by countertop and appliance tier, and any structural changes such as wall removal or footprint expansion.
Where the money goes
- Cabinetry
- 30--35%
- Labor
- 20--25%
- Countertops & backsplash
- 10--12%
- Appliances
- 10--15%
- Flooring & lighting
- 8--10%
- Permits & design
- 4--6%
- Contingency
- 8--10%
Directional shares of a typical kitchen budget. Your project will vary.
Typical timeline
- Most kitchen remodels run 4 to 8 weeks from demolition to final walkthrough. Cabinetry lead times, which run 8 to 16 weeks for semi-custom or custom, are the most common source of delay, so they are ordered early in the process.
Common questions
Answers before you call.
- Most Minnesota kitchen remodels fall between $25,000 and $175,000, depending on cabinetry, layout changes, and finish level.
- Most take 4 to 8 weeks from demolition to completion. Custom cabinetry lead times can extend the timeline if ordered late.
- Most remodels involving plumbing, electrical, or structural changes require a permit. A licensed Minnesota contractor pulls the required permits as part of the project.
- Look up the contractor through the Minnesota DLI license lookup tool. Confirm the license is active, matches the legal business name on your contract, and is the correct classification.
- Cabinetry is typically the largest single line item, followed by whether the layout changes.